很多施工队一听冷再生能省外运和新料钱,立马打电话问“550一天多少、250S一天多少”。但真到工地你会发现:主机转着,后面没撒布车,水泥靠人工扬;没洒水车,加水看天意;没压路机紧跟,拌完的混合料在太阳底下晒到初凝——非常后取芯取不出完整柱状样,返工那段比买新料还贵。
Many construction teams immediately call and ask, "How much is 550 per day and how much is 250S per day?" when they hear that cold recycling can save on transportation and new material costs. But when you actually arrive at the construction site, you will find that the main engine is spinning, there is no spreading truck behind, and the cement is manually lifted; No sprinkler truck, add water to see the will of heaven; Without a roller following closely, the mixed material is exposed to the sun until it reaches initial setting - and in the end, the core cannot be taken out to obtain a complete cylindrical sample. Rework the section is more expensive than buying new material.

这套工艺赚的就是“闭环”的钱,缺一环全断:
This process earns money in a "closed loop", with one loop missing and completely broken:
前面用粉料撒布车(陆达、徐工16–18方)把水泥/石灰按每平方用量均匀落下,电脑设定量建议拿实际称重复核,路拌法水泥剂量还要比配合比报告多加1%。
At the front, use a powder spreader (Landa, XCMG 16-18 cubic meters) to evenly drop cement/lime according to the dosage per square meter. The computer set quantity must be verified by actual weighing, and the cement dosage for road mixing method should be increased by 1% more than the mix proportion report.
中间冷再生机推着水车走,铣刨、破碎、加水、拌和一次完成,速度卡在4–10m/min,横向搭接不小于10cm。
The intermediate cold regeneration machine pushes the water wheel to complete milling, crushing, adding water, and mixing in one go, with a speed stuck at 4-10m/min and a horizontal overlap of not less than 10cm.
后面平地机整平,单钢轮稳压+胶轮收光,100m左右一段流水作业,别等水泥初凝再补压。
The leveling machine behind is used for leveling, with a single steel wheel stabilizing the pressure and a rubber wheel finishing. The process is carried out in a flow of about 100m, and do not wait for the initial setting of the cement before applying pressure.
机型别盲目上大:
Don't blindly increase the size of the model:
村道、园区、小区路,再生深8–15cm,国产550/600完全够用,机械传动还省油;国省干道、市政主路要啃20cm以上老基层或含水泥稳定层,直接上维特根2500/250S,转子扭矩和深度传感器稳,不会出现“表面铣完、底下留硬壳”的情况。
Village roads, industrial parks, and residential roads, with a regeneration depth of 8-15cm, domestic 550/600 are fully sufficient, and mechanical transmission is also fuel-efficient; National and provincial main roads, as well as municipal main roads, need to gnaw on the old base layer or cement stabilized layer of more than 20cm. They should be directly installed on the Wittgen 2500/250S, with stable rotor torque and depth sensors, and there will be no situation of "surface milling finished and hard shell left at the bottom".
合同里把三件事写死,比砍台班费有用:
Writing down three things in the contract is more useful than cutting off the cost of the TV crew:
报价含不含撒布车、操作手、油料、进出场费。
The quotation does not include the cost of the spreader, operator, fuel, and entry and exit fees.
计价方式:路况清楚按平米包干锁成本,复杂路段按台班但写明故障停机扣费规则。
Pricing method: For clear road conditions, the cost will be fixed per square meter, while for complex road sections, the cost will be charged based on the number of shifts but with clear rules for fault shutdown.
再生深度、水泥剂量、非常佳含水量写进附件,达不到钻芯强度由出租方配合返工。
The depth of regeneration, cement dosage, and optimal moisture content are included in the attachment. If the drilling core strength cannot be achieved, the lessor shall cooperate with rework.
济南周边5–10月设备紧,提前一周锁机带熟手,别等铣刨机到了再到处借压路机。
The equipment around Jinan is tight from May to October. Lock the machine and bring experienced hands one week in advance. Don't wait until the milling machine arrives before borrowing the roller everywhere.
本文由冷再生机租赁友情奉献.更多有关的知识请点击:http://www.sddhfjx.com我们将会对你提出的疑问进行详细的解答,欢迎你登录网站留言.
This article is a friendly contribution from Cold Recycling Machine Rental For more information, please click: http://www.sddhfjx.com We will provide detailed answers to your questions. You are welcome to log in to our website and leave a message





























公司地址:济南市槐荫区经一路273号群盛华城2号楼1-404
公司名称:山东途畅路桥工程有限公司
备案号: