水泥撒布车出租:撒布水泥的施工方法比较!!撒布车&人工
来源:https://www.sddhfjx.com/ 日期:2026-01-14

  人工撒布水泥的施工方法:

  Construction method of manually spreading cement:
01

  ⑴、水泥用量计算:老路段水泥稳定碎石冷再生设计剂量为5%,密度:2.137 g/cm3   厚度:0.25m 每平米水泥用量:0.25*2.137*0.05*1000=26.7125斤。加宽段水泥稳定碎石水泥剂量6%。密度:2.086 g/cm3 厚度0.15m 每平米水泥用量:0.15*2.086*0.06*1000=18.774公斤。

  ⑴ Calculation of cement dosage: The design dosage for cold recycling of cement stabilized crushed stone in the old road section is 5%, with a density of 2.137 g/cm3 and a thickness of 0.25m. The cement dosage per square meter is 0.25 * 2.137 * 0.05 * 1000=26.7125 pounds. The cement dosage for stabilizing crushed stone in the widened section is 6%. Density: 2.086 g/cm3 Thickness: 0.15m Cement dosage per square meter: 0.15 * 2.086 * 0.06 * 1000=18.774 kilograms.

  ⑵、打布水泥方格:半幅宽度为7.2m+4.58m=11.58m。纵向可分2.4*3+2.3*2划分,根据每平米水泥用量,老路5%水泥用量布控长度:100/26.7125/2.4=1.56m  即老路5%水泥用量布控为2.4*1.56;老路4.5%水泥用量布控长度:100/24.04125/2.4=1.73m  即老路4.5%水泥用量布控为2.4*1.73;加宽段布控长度:100/18.774/2.3=2.32m;即布控为2.3*2.32。

  ⑵ Laying cement grid: half width of 7.2m+4.58m=11.58m. Vertically, it can be divided into 2.4 * 3+2.3 * 2 sections. According to the cement consumption per square meter, the length of the old road's 5% cement consumption control is 100/26.7125/2.4=1.56m, which means the old road's 5% cement consumption control is 2.4 * 1.56; The length of the 4.5% cement consumption control for the old road is 100/24.04125/2.4=1.73m, which means that the 4.5% cement consumption control for the old road is 2.4 * 1.73; Widening section control length: 100/18.774/2.3=2.32m; that is, the control length is 2.3 * 2.32.

  ⑶、摊铺水泥:每个方格放足量合格的水泥两袋,人工拆开封口,用推板刮匀。布水泥段落长度和冷再生铣刨机速度速度相适应,一般在冷再生前60-80m,过长水泥将被风、或行车产生的气流刮走而造成损失。

  ⑶ Laying cement: Place two bags of qualified cement in each square, manually open the seal, and use a push plate to scrape evenly. The length of the cement section is adapted to the speed of the cold recycling milling machine, usually 60-80m before cold recycling. If the cement is too long, it will be blown away by the wind or the airflow generated by the vehicle, causing losses.

  粉料撒布车的施工方法:

  Construction method of powder spreading vehicle:

  ⑴、水泥运输车压力输入撒布车进行装料。

  ⑴ The pressure input of the cement transport vehicle is used to load the material into the spreading vehicle.

  ⑵、设定撒布水泥的宽度和厚度。

  ⑵ Set the width and thickness for spreading cement.

  ⑶、进行全自动均匀撒布。

  ⑶ Perform fully automatic and uniform spreading.

  本文由 水泥撒布车出租  友情奉献.更多有关的知识请点击  https://www.sddhfjx.com/   真诚的态度.为您提供为全面的服务.更多有关的知识我们将会陆续向大家奉献.敬请期待.

  This article is a friendly contribution from a cement spreader rental For more related knowledge, please click https://www.sddhfjx.com/ Sincere attitude To provide you with comprehensive services We will gradually contribute more relevant knowledge to everyone Stay tuned