冷再生机对于施工有什么要求?

来源:https://www.sddhfjx.com/ 日期:2022-02-22
1、乳化沥青再生与泡沫沥青再生压实度
1, emulsified asphalt regeneration and foam asphalt regeneration compaction degree
高速公路与一级公路的乳化沥青再生压实度需要达到90%以上,泡沫沥青再生压实度需要达到98%以上;二级及二级以下公路,乳化沥青再生压实度需达到88%以上,泡沫沥青再生压实度需要达到97%以上。每车道每检查两次。
The compactness of emulsified asphalt for Expressway and first grade highway needs to reach more than 90%, and the degree of regeneration and compaction of foam asphalt needs to reach more than 98%. For grade two and grade two highways, the compactness of emulsified asphalt needs to reach over 88%, and the degree of regeneration and compaction of foamed asphalt needs to reach more than 97%. Check twice per kilometer per lane.
2、含水率
2. Moisture content
冷再生机施工含水率需要符合基本规范要求,每三个工作日检验一次。
The construction moisture content of cold regenerator shall meet the requirements of basic specifications and be inspected every three working days.
3、沥青含量矿料级配
3. Asphalt content mineral aggregate gradation
发现沥青含量矿料级配异常时应随时检验,检验方法为油提筛分。
In case of abnormal asphalt content and mineral aggregate gradation, it shall be inspected at any time. The inspection method is oil extraction screening.
4、冻融劈裂强度比
4. Freeze thaw splitting strength ratio
冻融劈裂强度比应大于70%,每三个工作日检查一次。
The freeze-thaw splitting strength ratio shall be greater than 70%, and it shall be checked every three working days.
5、其他检查项目
5. Other inspection items
残留稳定度,干湿劈裂强度比,马歇尔稳定度,15℃劈裂强度等,需要每工作日检查一次,符合设计要求。
Residual stability, dry wet splitting strength ratio, Marshall stability, 15 ℃ splitting strength, etc. need to be checked every working day to meet the design requirements.
以上就是冷再生机对于施工质量的要求,公司经营冷再生机租赁,欢迎来电咨询!
The above is the requirements of cold regeneration for construction quality. The company operates cold regeneration machine rental. Welcome to inquire!