概述冷再生泡沫沥青冷再生机出租施工的技术流程!

来源:https://www.sddhfjx.com/ 日期:2020-09-28
  泡沫沥青冷再生施工技术,本质上是把泡沫沥青的一些优良特性运用到实际应用中的施工技术。但是,用户要想充分发挥技术优势,在实际施工过程中需要遵循以下流程:
  The cold recycling construction technology of foamed asphalt is essentially the application of some good characteristics of foamed asphalt to practical application. However, in order to give full play to the technical advantages, users need to follow the following process in the actual construction process:
  在施工过程中,冷再生机出租回来之后,要先用铣刨机对要铺筑的沥青面层进行清理。待检修的路面应磨平基层。其由装载车重新装载,之后铺设泡沫沥青混凝土。在这里需要提醒大家注意的问题是:此项冷再生技术在铺设新路面的过程中并不会受到天气条件的限制,即使在寒冷的天气和雨天,依然可以进行正常的施工作业。从这一点我们可以看出,它在当今市场上得到了广泛的应用。
  In the construction process, after the cold recycling machine is rented back, the milling machine should be used to clean the asphalt surface course to be paved. The pavement to be repaired shall be ground to the base course. It is reloaded by loading truck and then foamed asphalt concrete. Here we need to pay attention to the problem is: this cold recycling technology in the process of laying new pavement will not be limited by weather conditions, even in cold weather and rainy days, can still carry out normal construction work. From this we can see that it has been widely used in today's market.
  以上便是泡沫沥青在建筑施工中的冷再生技术。用户只要按上述工艺进行摊铺,效果是有保证的。
  The above is the cold recycling technology of foamed asphalt in construction. As long as users carry out paving according to the above process, the effect is guaranteed.
               冷再生机出租
  冷再生机出租在项目实施过程中,为了保证项目的效果,需要进行质量控制。那么,究竟应该怎么控制冷再生的质量问题呢?为保证冷再生的质量控制,应遵循以下三点:
  In order to ensure the effect of the project, quality control is needed in the process of project implementation. In order to ensure the quality control of cold regeneration, the following three points should be followed:
  一、原材料的各项试验必须在施工前进行,检验合格后方可使用。施工前需要对混合料进行多种试验,用于确认材料没有发生变化后方可正常施工。
  1、 All tests of raw materials must be carried out before construction and can be used only after passing the inspection. Before construction, a variety of tests should be carried out on the mixture to confirm that the material has not changed before normal construction.
  二、在施工的时候,需要随时检测混合料中粘结剂和外加剂的含量,这样得以保证施工的质量问题。
  2、 During the construction, it is necessary to detect the content of binder and admixture in the mixture at any time, so as to ensure the quality of construction.
  三、在施工的过程中,需要根据混合料的搅拌和加工性能,及时调整消耗的水量。
  3、 In the process of construction, it is necessary to adjust the water consumption timely according to the mixing and processing performance of the mixture.
  以上是关于冷再生泡沫沥青冷再生机施工的技术流程的介绍,希望对大家有所帮助,如想了解更多内容欢迎点击我们的冷再生机出租www.sddhfjx.com官网。
  The above is an introduction to the technical process of cold regeneration foam asphalt cold recycling machine construction. We hope to help you. If you want to know more about it, please welcome our cold recycling machine to rent. www.sddhfjx.com Official website.