欢迎访问山东途畅路桥工程有限公司网站!

冷再生机租赁

施工租赁热线

18264104888

您现在所在的位置 :首页 - 新闻中心 > 公司新闻

公司新闻

冷再生机的常用施工方案!

来源:https://www.sddhfjx.com/ 日期:2020-09-07
  根据原有道路结构和新设计方案的不同, 就地冷再生可以组合出多种施工方案!其实各种施工方案的工作原理都是一样, 区别是掺入材料的不同,加入的方法也有所不同。以水泥为添加料对沥青路面进行就地冷再生是常用的一种方案。
  According to the difference of the original road structure and the new design scheme, a variety of construction schemes can be combined by cold recycling in place! In fact, the working principle of various construction schemes is the same. The difference is that the mixing materials are different, and the adding methods are also different. It is a common scheme that cement is used as additive for cold in place recycling of asphalt pavement.
  在利用水泥进行就地冷再生时,外加料主要是水泥,水泥的通常用量按重量计在2%-5%之间比较合适。如果水泥的用量过多,容易使再生层变脆。同时还要加入适量的水。
  When cement is used for in-situ cold recycling, the main additive is cement, and the normal amount of cement is 2% - 5% by weight. If the amount of cement is too much, it is easy to make the regeneration layer brittle. At the same time, add appropriate amount of water.
  水泥的加入方法有两种,一种是利用人工或专用机械将水泥预先撒布在需要再生的路面上。这时水的加入方法,是通过冷再生机上所配备的微机控制系统从跟班作业的运水车内输送到冷再生机的拌和仓中。
  There are two ways to add cement. One is to spread the cement on the pavement which needs to be recycled by manual or special machinery. At this time, the water is added into the mixing bin of the cold regenerator through the microcomputer control system equipped with the cold regeneration machine from the water truck of the shift operation.
                 冷再生机租赁
  另一种方法是采用水泥稀浆搅拌输送车,将需要添加的水泥和水搅拌成水泥稀浆,再通过冷再生机上的控制系统将其输送到冷再生机的拌和仓中。
  Another method is to use cement slurry mixer truck to mix the cement and water needed to be added into the cement slurry, and then it is transported to the mixing bin of the cold regenerator through the control system on the cold regenerator.
  这种方法的优点就是在控制用量方面非常方便。因为在施工中冷再生机要分几个工作行程才能完成一个作业段内整幅路面的铣刨,而再生层的碾压要等到整个作业段全部施工工序完成之后才能进行,这就形成先铣刨的路面和后铣刨的路面到碾压时所等待的时间间隔相差很多。
  The advantage of this method is that it is very convenient to control the dosage. Because in the construction, the cold recycling machine needs to divide several working trips to complete the milling of the whole pavement in an operation section, and the rolling of the regeneration layer can only be carried out after the completion of all construction procedures in the whole operation section, which results in a lot of differences in the waiting time between the first milled pavement and the later milled pavement.
  感谢您的阅读,希望对您有所帮助,如您想要了解更多内容请继续关注我们的网站。
  Thank you for your reading and hope to help you. If you want to know more, please continue to pay attention to our website.
  • 上一条:冷再生机出租浅谈水泥路面冷再生机的发展分析!
  • 下一条:租赁冷再生机时需要注意哪些问题?
  • 相关产品: